Welcome to MTG Australia Pty LtdProject enquiries are accepted through the website enquiry form only.

Integrated systems testing

Testing the building as an integrated operating system.

MTG Australia assists with integrated systems testing so life safety, power, mechanical, fire, hydraulic, security and controls systems operate together under expected scenarios.

Integrated performance

Individual systems can pass tests while the building still fails as a whole.

Integrated systems testing addresses the interfaces between systems. It confirms whether a cause-and-effect matrix, fire mode strategy, emergency power arrangement, security interface or controls sequence works in the completed facility.

MTG Australia can help review the specification, define test scenarios, attend witness testing, record defects and assist the project team to close out unresolved issues.

Integrated testing scope

  • Fire mode cause-and-effect review
  • Emergency power and generator/UPS interface review
  • Mechanical shutdown, smoke control and stair pressurisation interface review
  • Security, access control and door release sequence review
  • Hydraulic, fire pump and alarm interface considerations
  • BMS, controls and monitoring verification
  • Issue logs, test evidence and close-out reporting

Recommended test planning sequence

Review intent

Confirm the fire strategy, services design, specifications, controls logic and contractual testing requirements.

Define scenarios

Prepare realistic operating scenarios that involve multiple systems, trades and responsible parties.

Witness and record

Attend tests, record pass/fail outcomes, identify defects and track close-out evidence.

Integrated testing gap review

MTG Australia can review your current specification, commissioning plan or handover evidence and identify where integrated system performance has not been adequately defined or tested.

Request a review